Greater Noida Industrial Development Authority has empowered the
Architects registered with the Council of Architecture (COA) for Sanction /
Approval of Building Plans/ Occupancy Certificate on individual residential
plots allotted by Greater Noida Industrial Development Authority on the
following terms and conditions-
For Building Plan Approval on residential plot other than group housing-
1.
The Building plan prepared and signed
by the Architect, registered with COA, when submitted shall be deemed as
sanctioned. At the time of submission of building plan following documents need
to be submitted.
(i) Declaration
on Rs.10/- stamp paper duly signed by the Architect stating that the Building
Plan submitted by him/ her is in accordance with the Zonal Plan and building
Regulations / Directions applicable from time to time of the Greater Noida
Industrial Development Authority.
(ii)
Documents as listed in checklist A of
Appendix-1in Building Regulation 2002.
2.
In case of revision of building plan
in addition to all above mentioned documents revision fees and original plan,
are to be submitted.
3.
On submission of the aforesaid papers
at the Customer Relation Cell a receipt shall be given on the checklist and the
plans. The receipt shall be deemed as sanction letter.
4.
If at the time of scrutiny by the
Authority (within one month of submission of drawings ) any mistake is found,
architect signing the drawings shall be held responsible for the same.
Completion plan for Occupancy certificate on residential plot other than
group housing-
1.
The Building Completion plan prepared
and signed by the Architect, registered with COA, when submitted shall be deemed
as Occupancy Certificate. At the time of submission following documents need to
be submitted �
(i) Declaration on Rs.10/- stamp paper duly
signed by the Architect and allottee stating that the Building constructed by
the allottee is constructed under the supervision of the Architect and is in
accordance with the Zonal Plan and Building Regulations / Directions applicable
from time to time of Greater Noida Industrial Development Authority.
(ii) Two post card size photographs of building
constructed (one front and one backside) duly attested by the Architect with
date and plot number.
(iii) All the documents listed as per checklist A
of Appendix-9 in Building Regulations 2002.
2
On submission of the aforesaid papers
the Authority shall give a receipt on the checklist and that receipt shall be
deemed as occupancy/ completion certificate.
3
If at the time of scrutiny by the
Authority (within one month of submission of drawings) any deviation from the
drawings or Zonal Plan, Building Regulations/ Direction as applicable from time
to time is found, architect signing the drawings shall be held responsible for
the same.
GENNERAL INFORMATION
1.
The cases in which sanction /
completion have been received will be scrutinesed by the Authority.
2.
In case mistake is found in drawing
for sanction and date for completion action shall be taken against the
Architect as per Greater Noida Industrial Development Area Building Regulation
2002.
3.
If a Sanction/Completion submitted
with Authority, is found against the Building Regulations, Planning and
Development Directions and Zonal Plan, the Authority can cancel such plan. On
cancellation of such plan lease holder or Architect shall not claim any damages
against the Authority.
4. All Architects, registered with
Council of Architecture, shall be issued a Record Book.
4.1 This Record book shall be produced
at Customer Relation Cell at the time of submission of building plan for
approval/ occupancy so that corresponding entry for Plot Number can be made.
4.2 This Record book shall be issued on
producing of following documents at Customer Relation Cell by
Architect/representative:-
a) Original COA Certificate.
b) Any one of the original Identity
Proof
i) Vote I Card.
ii) PAN Card.
iii) Driving License.
Further Architect will also submit duly self
attested copy of aforesaid documents and signature & address of Architect
Attested by Bank Manager.
The aforesaid orders are being issued with the
approval of Chief Executive Officer and shall be implemented with immediate
effect.